Sprinkler / Alarm Building Plan Requirements

Fire Sprinkler and Fire Alarm Requirements
The following must be submitted with building plans:

If no fire alarm or fire-sprinkler devices will be affected by the construction being permitted, you must note this on the permit application.
Multifamily building plans for new construction and additions or alterations must include a full set of fire sprinkler and fire alarm plans.
The fire alarm plans must include data on all equipment, devices and wire, line loss and battery calculations, sequence of operations and a riser diagram.
The fire sprinkler plans must include data on all heads, hangers, pipes, fittings and hydraulic calculations. For new construction, details for underground pipes, risers, fire department connections and post indicator valves (PIV) should be included.

Fire Line Underground, Fire Sprinkler and Fire Alarm Requirements for Commercial Construction
Building plans for new construction and for additions, alterations or renovations must include a full set of plans as follows:

Fire alarm plans must include data on all equipment, devices, wires, line loss and battery calculations, sequence of operations and a riser diagram.
Fire line underground plans must include data on all pipes, valves, backflow prevention devices, fire department connections, fire hydrants and PIVs.
If no fire alarm or fire sprinkler devices will be affected by the construction being permitted, you must note this on the permit application.
The fire sprinkler plans must include data on all heads, hangers, pipes, fittings and hydraulic calculations.

Structural Fire Wall Inspection
Work involving fire walls, tenant separation walls, floors, ceilings and kitchen and bathroom remodeling will require a structural fire wall inspection. For inspections, contact 239-213-5020.