The City of Naples has 112 travel lane miles and 58 miles of sidewalk that we maintain. If you would like to report a pothole or a sinkhole on a City street, or a broken sidewalk or trip hazard, please call 239-213-5000 or fill out the form in the Request Tracker.
Roadway Paving Schedule (October 2025):
Beginning Monday, October 6, 2025, the City of Naples and Pavement Maintenance Inc. will mill and resurface the city roadways listed below. The work is tentatively scheduled to be completed in five (5) business days per area, weather permitting. Pavement Maintenance Inc. will start in the Park Shore Area and work their way through the Moorings area, Old Naples area, and finish in the Port Royal and Royal Harbor Area.
- Whispering Pine Lane – From Crayton Rd to West Blvd – 1 Day Milling, 1 Day Paving
- Crayton Road – From Neapolitan Way to Seagate Dr – 2 Days Milling, 2 Days Paving
- Neapolitan Lane – From Neapolitan Way to Belair Lane – 1 Day Milling, 1 Day Paving
- Old Trail Way – From Old Trail Dr to Terminus – 2 Days Milling, 2 Days Paving - COMPLETED
- Regatta Road – From Harbour Dr to Anchor Rode Dr – 2 Days Milling, 2 Days Paving - COMPLETED
- Bollard Place – From Crayton Rd to Terminus – 1 Days Milling, 1 Days Paving
- Coral Drive – From Murex Ln to Mandarin Rd – 1 Days Milling, 1 Days Paving
- Broad Avenue North – From 3rd St N to Palm Cir W – 1 Days Milling, 1 Days Paving
- 6th Lane North – From 10th St N to 12th St N – 1 Days Milling, 1 Days Paving
- 12th Street South – From 1st Ave S to Terminus – 2 Days Milling, 2 Days Paving
- 7th Avenue South – From E Lake Dr to Park St – 1 Days Milling, 1 Days Paving
- 4th Street South – From 14th Ave S to 8th Ave S – 2 Days Milling, 2 Days Paving
- Shell Alley – From Gulf Shore Blvd S to Gordon Dr – 1 Days Milling, 1 Days Paving
- Cutlass Lane – From Gordon Dr to Terminus – 2 Days Milling, 2 Days Paving
- Cove Lane – From Gordon Dr to Terminus – 1 Days Milling, 1 Days Paving
- Tarpon Road – From Marlin Dr to Terminus – 4 Days Milling, 4 Days Paving
- 2nd Street South – From 5th Avenue South to Broad Avenue – 3 Days Milling and Paving
Traffic control and warning signs will be installed in the work zone. Most of the work will impact vehicular traffic; however, one lane will remain accessible, using flagmen to direct traffic.
Motorists, bicyclists, and pedestrians should be alert for construction workers and equipment in and around the roadway. They are encouraged to allow additional time in their schedule for potential delays. Resident cooperation and patience are appreciated during this process.
Questions concerning this project should be directed to the City of Naples’ Streets and Stormwater Department: Dave Rivera, at 239-213-5011 or drivera [at] naplesgov.com (DRivera[at]naplesgov[dot]com).